Sunday 14 October 2012

The Approved Masterplan for Battersea

Phase 1 development
Following an architectural competition in late 2010 the Phase One design team were appointed. In January 2011. This team was re-appointed in August 2012 following the change in ownership of the site:
  • Building RS1A – Ian Simpson Architects.
  • Building RS1B – de Rijke Marsh Morgan Architects
  • Landscape – Exterior Architecture and LDA Design.
  • Rafael Viñoly will remain as Masterplan Architect for the site and will continue to oversee the detailed delivery of the project.
  • Construction on Phase One is scheduled to commence in 2013 with completion expected in 2016.
  • Renovation work on the Grade II* listed Power Station is due to commence in 2013.
Riverside wall

Building RS-1A - Ian Simpson Architects

These are residential buildings. The elevations have been carefully designed to complement the simple, elegant planar proportions of the power station. The palette of materials and emphasis on horizontal expression provide a contrast to the solidity and verticality of the power station’s masonry exterior.

RS-1A - view south across river

Landscape RS-1A - LDA

Phase One will deliver the first section of the new Power Station Park. The
park will form an exciting new public waterfront green-space and will create a new setting for the Power Station. The central section of the park will be a large lawn where events can take place. It will also be a place ideal for sunbathing, picnicking and enjoyingviews of the Power Station, the river and London’s wider panorama. 




No comments: